Devices mounted
All devices are mounted to our rack and partially powered up.At this point, some of the VM is back online. Our client portal and cloud cluster still in installation process….
All devices are mounted to our rack and partially powered up.At this point, some of the VM is back online. Our client portal and cloud cluster still in installation process….
All devices have been unracked. We are now transport all devices to new data center.
We will gradually shutdown all VM in next 25 minutes and power off all devices for unrack purpose. If you are on dedicated server or colocation, you are advised to…
Some of the hardware has been transported to the new data center. Network is now ready. We will begin unrack the remaining production servers including all VM nodes on planned…
This is a gentle reminder to remind you that we will be performing hardware migration on coming 26th Oct 2018.